Additional 2017 Sidewalk Projects (from the City Newsletter)
Good news, additional sidewalks are planned for Peachtree Corners in 2017. Following are four projects that will add nearly 2,600 feet by the end of the year.
1. Peachtree Corners Circle – approximately 2,000 feet of sidewalk will run from Peachtree Parkway (near Noble Fin restaurant) to the intersection of Medlock Bridge Road.
2. Corners Parkway – approximately 1,300 feet of sidewalk will be installed from Crooked Creek to Kiveton; additionally 1,300 feet of sidewalk will be installed from Woodhill Drive to Holcomb Bridge Road.
3. Technology Parkway South – Nearly 2,400 feet of sidewalk is scheduled to be installed from the corner of Technology Parkway to Peachtree Industrial Boulevard.
4. Frank Neely Road – A new sidewalk will be installed between Dove Field Court and Spalding Drive.